PEA completed (Jan 2024); permitting underway (FAST-41, state permit filed, BIA consultation ongoing); production forecast 2028-29 • PEA
Overview
Country
United States
Region
New Mexico
Current status
5 projects in this company presentation
Report date 2026-04-01
Laramide Resources Ltd. • LAM.TO • 5 projects
PEA completed (Jan 2024); permitting underway (FAST-41, state permit filed, BIA consultation ongoing); production forecast 2028-29
Permit status
NRC production license in place; state permitting advancing; BIA right-of-way under consultation
Strategic shareholders
Boss Energy, ETFs, Other Institutional
Mine type
ISR
Classification
Project stage
Developer
Substage
PEA
Active milestone
Permitting (FAST-41, state permit, BIA ROW)
Completed milestones
PEA (Jan 2024)
Resources
Inferred
50.8 Mlb
Inferred grade
750.0 ppm
Total resources
50.8 Mlb
Cutoff grade
200.0 ppm
Endowment
Core endowment
50.8 Mlb
Grade
750.0 ppm
Field recovery rate
68.0%
Financials
Production rate
1.0
Total production
31.2 Mlb
Life of mine
31.0 years
Uranium price used
$75.00/lb
Recovery rate
68.0%
Post-tax NPV8
$249M
Post-tax IRR
56.0%
Post-tax cash flow
$1,000M
Capex
$47.5M
AISC
$34.83/lb
Cash costs
$24.70/lb
Strategics
PEA
2024-01-01
FID
2027-04-01
Production
2028-01-01
Notes
Highlights
Licensed central processing plant (3 Mlb/yr capacity); scalable ISR resource (~55 Mlbs inferred); direct exposure to U.S. supply needs; positioned for long-term utility contracting.
Country attractiveness
U.S. government support for domestic uranium supply; critical mineral designation; federal support for supply chains.
Resource context
~55 Mlbs U3O8 inferred ISR resource; Crownpoint 5.1 Mlbs inferred under same license.
Permit context
NRC license in place; FAST-41 federal permitting; state and BIA permits advancing.
Technical context
ISR technology; 68% recovery assumed in PEA; further test work may improve recoveries.